The mechanical scope of the work included the total installation of five 150-MW radiant heat boilers with auxiliaries and the erection of 30,000 tons of pipes, steel structures and equipment. A total of 3 million man-hours was expended, with a workforce peaking at 1,200 men. Special welding was required for carbon, alloy and stainless steel, CUNIFE cladded pipe, copper pipe and fiberglass. MAC also carried out all painting, insulation and lagging.
The work included: