YAMAMA CEMENT PLANT
Project Name : Yamama Cement Plant 3000 T/Day Extension
Location : Riyadh , Saudi Arabia
Client

: Yamama Cement Company

Construction Period : 23 Months

Summary

 

The civil works were carried out on a design and build basis as part of a 50:50 joint venture with the German company Bilfinger and Berger The job entailed all design, supply and delivery of materials as well as construction.